歡迎訪問山東途暢路橋工程有限公司網站!

冷再生機租賃,水泥撒布車出租

施工租賃熱線

18264104888

您現在所在的位置 :首頁 - 新聞中心 > 公司新聞
公司新聞

冷再生機對于施工有什么要求?
來源:http://www.cansolv.cn/ 日期:2022-02-22
1、乳化瀝青再生與泡沫瀝青再生壓實度
1, emulsified asphalt regeneration and foam asphalt regeneration compaction degree
高速公路與一級公路的乳化瀝青再生壓實度需要達到90%以上,泡沫瀝青再生壓實度需要達到98%以上;二級及二級以下公路,乳化瀝青再生壓實度需達到88%以上,泡沫瀝青再生壓實度需要達到97%以上。每車道每公里檢查兩次。
The compactness of emulsified asphalt for Expressway and first grade highway needs to reach more than 90%, and the degree of regeneration and compaction of foam asphalt needs to reach more than 98%. For grade two and grade two highways, the compactness of emulsified asphalt needs to reach over 88%, and the degree of regeneration and compaction of foamed asphalt needs to reach more than 97%. Check twice per kilometer per lane.
2、含水率
2. Moisture content
冷再生機施工含水率需要符合基本規范要求,每三個工作日檢驗一次。
The construction moisture content of cold regenerator shall meet the requirements of basic specifications and be inspected every three working days.
3、瀝青含量礦料級配
3. Asphalt content mineral aggregate gradation
發現瀝青含量礦料級配異常時應隨時檢驗,檢驗方法為油提篩分。
In case of abnormal asphalt content and mineral aggregate gradation, it shall be inspected at any time. The inspection method is oil extraction screening.
4、凍融劈裂強度比
4. Freeze thaw splitting strength ratio
凍融劈裂強度比應大于70%,每三個工作日檢查一次。
The freeze-thaw splitting strength ratio shall be greater than 70%, and it shall be checked every three working days.
5、其他檢查項目
5. Other inspection items
殘留穩定度,干濕劈裂強度比,馬歇爾穩定度,15℃劈裂強度等,需要每工作日檢查一次,符合設計要求。
Residual stability, dry wet splitting strength ratio, Marshall stability, 15 ℃ splitting strength, etc. need to be checked every working day to meet the design requirements.
以上就是冷再生機對于施工質量的要求,公司經營冷再生機租賃,歡迎來電咨詢!
The above is the requirements of cold regeneration for construction quality. The company operates cold regeneration machine rental. Welcome to inquire!
  • 上一條:水泥撒布車適應在哪些方面使用?
  • 下一條:冷再生機的運行要如何把控?
  • 相關產品: